Cohen Quad – a quick (visual) recap

It’s been over 18 months now since the original Ruskin College buildings were demolished, the façade anchored in place, and 14,200 tons of earth removed in 710 lorry loads. Today, much of the core structure is completed, the auditorium is in place, and the glazing and roofing are now being put in place.

Each week, Fran Monks (Friend of Exeter) has taken a photograph of the site from the roof of her home in Worcester Place. We’ve put them all together in a time-lapse video which you can view here:

https://www.youtube.com/watch?v=MYRJHKd7-CU

Watch as we excavate into the basement, look out for the arrival of the big red crane, see the creation of the arched colonnade, view the construction of each floor, and be amazed at the building of the auditorium with its signature wish-bone rafters! The video finishes with most of the building swathed in weatherproof plastic, but you can still catch a glimpse of the glazing and rimex roofing.

Progress report: Cohen Quad is watertight and works have begun internally

We are pleased to report that work at Cohen Quad is progressing well and the main site activities are now focused on fitting out the building’s contents.

One of the last windows to be fitted – an impressive dormer window on the fourth floor with exceptional views over Jericho – was installed in March and the building is now fundamentally watertight. This has allowed the internal fit-out to begin, including the interior joinery and plaster boarding.

dormer-window-1

dormer-window-2

The dormer window with its exceptional views over Jericho

The wiring has been completed in the basement and on the ground floor and next week work will begin on the interior stonework on these floors. Meanwhile the electricians have moved to the first floor as they work their way up the building.

On the outside the first Rimex metal roof tiles have been fitted to the building’s exterior. These will give Cohen Quad its distinctive metallic roof and will also cover the exterior of some walls. Panel by panel the exterior of Cohen Quad will take shape and come the end of June the large crane that has dominated the site for many months will be removed, making it possible to see clearly how the finished building will look.

rimex-roof-tiles

Fitting the Rimex metal roof tiles